Skaros Stairs Co. of Moore designs and builds factory-made premium wooden stairs for homes

Skaros Stairs Co. of Moore designs and builds factory-made premium wooden stairs for homes. The manufactured stair components (spindles, risers, hangers, hand rails) permit installation of stairs of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2011 are as follows.
                Overhead Cost Pools                                                                      Amount
                Purchasing                                                                                          $ 57,000               
                Handling materials                                                                           82,000  
                Production (cutting, milling, finishing)                                     210,000
                Setting up machines                                                                       85,000  
                Inspecting                                                                                           90,000  
                Inventory control (raw materials and finished goods)      126,000
                Utilities                                                                                                 180,000
                Total budget overhead costs                                                      $830,000             
For the last 4 years, Skaros Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2011, 100,000 machine hours are budgeted.
     Anthony Morse, owner-manager of Skaros Stairs Co., recently directed his accountant, Neal Seagren, to implement the activity-based costing system that he has repeatedly proposed. At Anthony Morse\'s request, Neal and the production foreman identify the following cost drivers and their usage for the previously budgeted overhead cost pools.
Activity Cost Pools                                           Cost Drivers                                                        Expected
Use of
Cost Drivers
Purchasing                                                         Number of orders                                           600        
Handling materials                                          Number of moves                                           8,000    
Production (cutting, milling, finishing)     Direct labor hours                                           100,000
Setting up machines                                      Number of setups                                           1,250    
Inspecting                                                           Number of inspections                                  6,000    
Inventory control                                            Number of components                                               168,000
(raw materials and finished goods)
Utilities                                                                 Square feet occupied                                     90,000  
David Hannon, sales manager, has received an order for 280 stairs from Community Builders, Inc., a large housing development contractor. At David\'s request, Neal prepares cost estimates for producing components for 280 stairs so David can submit a contract price per stair to Community Builders. He accumulates the following data for the production of 280 stairways.
                Direct materials                                                                $103,600
                Direct labor                                                         $112,000
                Machine hours                                                  14,500
                Direct labor hours                                            5,000
                Number of purchase orders                        60
                Number of material moves                         800
                Number of machine setups                         100
                Number of inspections                                  450
                Number of components               1                              6,000
                Number of square feet occupied              8,000
Requirement:
  1. Compute the predetermined overhead rate using traditional costing with machine hours as the basis.
  2. What is the manufacturing cost per stairway under traditional costing?  
What is the manufacturing cost per stairway under the proposed activity-based costing?